- STUDY BY NRG-ORION
- EQUIPMENT PROCUREMENT BY NRG-ORION
- SOLON BLUE 220/03 P/V panels (215Wp) x 92pc.
- PESOS support system, a support system with (2) variable axes and astronomical control.
- SMA, 3XSMC 7000TL inverters.
- SMA, WEBBOX recording - communication system.
- INSTALLATION BY NRG-ORION
- MONITORING - MAINTENANCE BY NRG-ORION
The “GENI GIOLI” and “AGIA KYRIAKI” projects were successfully connected on 28.08.2009, while the “XIRO MONASTIRI” project was connected on 02.09.2009. On the basis of the study carried out using the PV-SOL programme of Dr VALENTIN ENERGΙΕSOFTWARE GmbH, each project is expected to deliver 29,531.54 kWh per year.