«ENERBAK» GEORGANADES, TRIKALA 2 x 99,00 kWp

General view of the project

General view of the project General view of the project
  1. STUDY BY NRG-ORION
  2. EQUIPMENT PROCUREMENT BY NRG-ORION
    • SOLON 450xBLUE 220/03 P/V panels (polycrystalline, 220Wp).
    • SCHLETTER PVMAX2 support system, a fixed system made with aluminium and stainless steel joints.
    • SMA, 9xSMC11000TL inverters.
    • SMA, WEBBOX Recording-communication system.
  3. INSTALLATION BY NRG-ORION
  4. MONITORING - MAINTENANCE BY NRG-ORION

Installation of the 2 projects by the technical staff of NRG-ORION started on 15.10.2008, when the investor had completed all building works, and was completed on 25.11.2008; both projects were connected successfully on 28.11.2008. On the basis of the study carried out using the PV-SOL programme of Dr VALENTIN ENERGΙΕSOFTWARE GmbH, each project is expected to deliver 117,150 kWh per year.

«ENERBAK» GEORGANADES, TRIKALA 2 x 99,00 kWp

Strategic Partners

NRG-ORION

Office, Laboratory & Pilot plant:
Vathylakkos, 57 011, Thessaloniki
Τel: (+30) 231 0566511
e-mail: info@nrg-orion.gr

Office:
20 Valaoritou str, 546 25, Thessaloniki
Τηλ: (+30) 231 0566511
e-mail: info@nrg-orion.gr