- STUDY BY NRG-ORION
- EQUIPMENT PROCUREMENT BY NRG-ORION
- SOLON 441xBLUE 220/07 P/V panels (polycrystalline, 225Wp).
- EXALCO support system, a fixed system made with aluminium and stainless steel joints.
- SMA, 9xSMC11000TL inverters.
- SMA, WEBBOX Recording-communication system.
- INSTALLATION BY NRG-ORION
- MONITORING - MAINTENANCE BY NRG-ORION
The project was connected to the PPC network on 14.08.2008, while the entire project was delivered, together with the “PAMVOTIS 2” project, on 05.09.2008. On the basis of the study carried out using the PV-SOL programme of Dr VALENTIN ENERGΙΕSOFTWARE GmbH, this project was expected to deliver 109,247 kWh per year. After 1 full year of continuous operation the P/V plant delivered 144,930 kWh i.e. 32.7% more energy than expected.